Weekend closure planned for repair work on SR 529 Snohomish River Bridge

EVERETT — Replacing critical machinery on the State Route 529 Snohomish River Bridge near Everett will close the southbound span this weekend.

Closure information:

  • • 8 p.m. Friday, Sept. 20 to 5 a.m. Monday, Sept. 23 — Southbound SR 529 will be closed between Interstate 5 and the bridge. The I-5 exit to southbound SR 529 will also be closed. Drivers who need to reach Smith Island can enter SR 529 at State Street in Marysville or follow a detour route on southbound I-5 to northbound SR 529.

During the closure, contractor crews working for the Washington State Department of Transportation will replace heavy pieces of machinery that operate the southbound lift span. The machinery is showing signs of wear and fatigue, including cracking, after 60 years of hoisting and lowering two counterweights weighing a total of 250 tons. The bridge averages about 600 openings each year.

The drawspan machinery is housed in two towers 80 feet above the southbound lanes. Crews will use a large crane to remove the old machinery in the northern-most tower and lift the new pieces into place.

A second closure of southbound SR 529 is also planned for the weekend of Sept. 28-29. Northbound SR 529 is not affected by this work.

Work on this $3.2 million project will be complete in October.

We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.

Read the Dec 13
Green Edition

Browse the print edition page by page, including stories and ads.

Browse the archives.

loading...