Airport developments on hold due to economy

A few more trees went down last week in preparation for the proposed new fire station in Smokey Point. The fire station is currently in design phase and construction is on hold due to economic issues.  -
A few more trees went down last week in preparation for the proposed new fire station in Smokey Point. The fire station is currently in design phase and construction is on hold due to economic issues.
— image credit:

ARLINGTON — Two major projects at the airport may have to wait due to economic challenges, according to Airport Manager Rob Putnam.

While clearing for the proposed fire station at the corner of 43rd and 172nd proceeded last week, the construction schedule is on hold for now.

Since the site is on Arlington Airport property, Putnam coordinated the clearing project. He said they made about $10,000 on the timber.

“The total value of the timber was $45,000, but after the cost of hiring Carlson Logging to do the work, we only made about $10,000,” Putnam said.

Across the airport, an expansion on the airport office may also be held off until later.

“We were hoping to present the airport office design for initial review and launch the permitting process next week,” Putnam said.

“But if our major tenant can’t move in, then that will hold up the project.”

The proposed expansion was developed on the proposal that the Washington State Department of Transportation Aviation Division would be a major tenant.

“I’ve got money to get started, but part of it is revenue bonds and if DOT can’t move in, that will impact the process. It’s DOT’s rent that would pay back the revenue bonds.”

In preparation for that expansion, a large fir tree near the airport office was also removed.

“We didn’t make any money on that one because it cost so much to take it down piece by piece,” Putnam said.

The city administrator confirmed that the new station No. 48 is on hold, due to the economy and drop in sales tax and real estate excise tax.

Although the design process will continue, and a remodel on the old Station No. 46 will go forward.

“We’re a go on the airport office,” said Allen Johnson.

Our Mobile Apps

Community Events, April 2014

Add an Event
We encourage an open exchange of ideas on this story's topic, but we ask you to follow our guidelines for respecting community standards. Personal attacks, inappropriate language, and off-topic comments may be removed, and comment privileges revoked, per our Terms of Use. Please see our FAQ if you have questions or concerns about using Facebook to comment.
blog comments powered by Disqus

Read the latest Green Edition

Browse the print edition page by page, including stories and ads.

Apr 19 edition online now. Browse the archives.